Remaining Limitations (post-IESS) with ez2view v9.9.5.41 to 25th Sept 2024

On 27th May 2024 we published ‘ez2view ‘Transition Release’ in preparation for IESS’ in parallel with the release of v9.9.3.351, and in anticipation of the IESS Market Change.

1)  The bulk of that market change went live on Monday 4th June 2024

2)  On 28th April 2024 we published ‘What is IESS, and why is it relevant to ez2view’.

3)  There’s more information collated on the IESS change under this category at WattClarity®.

 

Known Limitations, as at 27th May

Back in May (with the ‘Transition Release’), we also shared ‘Known Limitations with the ‘Transition Release’ of ez2view on 27th May 2024’.

 

Subsequent upgrades

On Friday 27th September 2024 (last week) we shared ‘Some of the enhancements made to ez2view since the v9.9.3.351 ‘Transition Release’ (to v9.9.5.41)’ to summarise some of the enhancements made to the software since that time.

In that article we linked through to this article, in which we update the table presented on 27th May to highlight that we’ve addressed most of the known issues, with only these remaining.


This article is also linked in the title bar of the v9.9.5.* installed software.

 

Remaining Issues, as at 30th September
(from list on 27th May)

Following from the publication of the Known Issues at 27th May, we have been working to address these known issues (interlaced with development of new functionality).

I’ve retained the left-hand column for ease of reference, but have changed the right-hand column to summarise if addressed or not.

Known Limitations
at v9.9.3.351
on 27th May 2024
Is this resolved (at v9.9.5.41), or is it a Remaining Issue?
Predispatch bids in real time not displayed from Private Data This issue was rectified as described in the note ‘Enhancements already made, beyond the Transition Release of ez2view’.
Temporary double-counting of Maximum Capacity for existing batteries. There is nothing for us to do here … this note was more for your information.  It’s a function of how the AEMO is transitioning BDUs:

  • a process that is not yet complete for all batteries; and
  • which you’ll continue to see, in any case, if you time-travel back to a period where transitions were in progress.

Note that (on 16th June) we published an update in ‘What to expect (in ez2view) when bi-directional units emerge’.

Bid Stack for BDUs for Regulation FCAS bids We have not yet implemented a collective representation of Regulation FCAS bids across the 20 bid bands of a BDU.

Refer to the earlier note for more detail.

Note that we have ascertained what needs to be done, just have not yet completed the implementation.

Export to CSV
temporarily disabled
in ‘Bids & Offers’ widget
This has been resolved:

  • For ENERGY bids
  • For Contingency FCAS bids

… but it remains outstanding for Regulation FCAS bids for BDUs, because of the above.

‘Bids Details’ widget This has been resolved:

  • For ENERGY bids
  • For Contingency FCAS bids

… but it remains outstanding for Regulation FCAS bids for BDUs, because of the above.

‘Unit Dashboard’ widget This widget has been substantially upgraded, as noted in  ‘Enhancements made, thus far, to ‘Unit Dashboard’ widget (to v9.9.4.217)’.
‘Station Dashboard’ widget The principles used in the upgraded Unit Dashboard widget (described here) have been flowed through to the Station Dashboard widget.

In this case the application of Conformance Status has been modified to take account of multiple units, and the possibility of Aggregate Dispatch Conformance group.

Note that this widget:

  • Opens as ‘Station Dashboard’ widget;
  • But is still listed as ‘Station Details’ widget in the ez2view explorer (this is something we’ll correct shortly).

—

The earlier note in May 2024 spoke about broader plans for enhancing this this widget, which are independent of these IESS related notes.

‘Constraint Dashboard’ widget This widget has been substantially upgraded, as noted in ‘Enhancements made, thus far, to ‘Constraint Dashboard’ widget (to v9.9.5.41)’..
Trends Engine We’ve delivered the enhancements required (with respect to IESS changes).
‘Swim Lanes’ Widget We’ve delivered the enhancements required (with respect to IESS changes).
‘NEM Map’ Widget We have completed all that’s required in relation to this widget (from an IESS perspective) .  For batteries (whether transitioned to BDU or not) the current behaviour is as follows:

  • For battery discharge in a region, add up any positive numbers for individual Fuel Type = Battery discharging, either:
    • BDU discharging; and/or
    • Non-transitioned battery generator discharging;
  • For battery charging in a region, add up any negative numbers for individual Fuel Type = Battery charging, either:
    • BDU charging; and/or
    • Non-transitioned battery load charging.

—

Separate to this, we have identified a number of other potential enhancements to the ‘NEM Map’ widget, but these are being assessed and prioritised as part of our broader iterative development method.

Fuel Type for DC-coupled hybrid Nothing further required, here.

(If and) when the DC-coupled hybrid units appear in the AEMO data, they will present as Fuel Type = “Other”.

No ‘CPD Price’ during certain OCD periods Nothing is required from an IESS implementation perspective.

—

Separate from this, we have identified two enhancements for future releases (after v9.9.5.41):

  • As a small enhancement (soon) there will be some form of tool tip added to help clarify when OCD is the reason that “–” is shown rather than a calculated price
  • A much larger development (not imminent) is to calculate, next day public, this data from other (i.e. non EMMS) sources in cases of OCD.
‘NEM Summary Stats’ Widget We have done all we plan with this widget.

—

We still have broader questions about the usefulness of this particular widget, and are likely to remove (or reconfigure) in future.

‘[REGION] Summary Stats’ Widgets We have done all we plan with this widget.

—

We still have broader questions about the usefulness of this particular widget, and are likely to remove (or reconfigure) in future.

 

We trust the above will prove useful?